The Accommodation
I restructured a client's payment schedule as a courtesy, and the bankruptcy court used that decision as evidence I knew they were in financial trouble.
In 2006 my agency was brought in to build the digital backbone of one of the most ambitious mobile startups in the country.
The client was one of the original MVNOs. If the acronym means nothing to you, here is the short version: before the iPhone existed, this company was already trying to build what the iPhone would eventually become. A mobile virtual network operator. A company that did not own towers but leased them, then built products on top of the network. They were moving fast and had the capital to prove it.
We landed the project through a pitch I will save for another issue. What I will say is that it involved chocolate chip cookies, cold milk, and a COO who declared we had quite a set of cojones. We walked away with a $360,000 contract to design and build their complete online ordering, activation, and account management platform. The system had to serve both customers managing their devices and the company managing their media plans. It was a serious build.
Two weeks later my core team and I were in Hollywood.
The company had taken over the studio where the hit television show “24” was filmed. Their offices were actual sets. We set up for our kickoff meeting in the fictional Situation Room where Jack Bauer spent four seasons planning operations. One of my team members discovered the hard way that the wall outlets were props. Several laptops stopped working before we figured out why.
Two long rows of over 100 live call agents were processing customer orders in real time. This was not a company behaving like it was in trouble. This was a company that looked like it was already winning.
The contract was structured as six installments of $60,000. A clean, predictable payment schedule. Easy to plan around. We had signed it, started work, and everything was on track.
Then the request came in.
The internal team was growing so fast that accounting could not keep up. They were onboarding a new CFO to get ahead of the curve. In the meantime, could we split the remaining installments to help manage their cash flow? Same total. Same scope. Same timeline. Smaller payments, more frequent. Just a different cadence for the money already committed.
It seemed like a reasonable ask. I was not giving anything up. I was helping a good client navigate a temporary internal issue. The kind of accommodation you make when you trust the people across the table.
I added a clause to our memo of understanding. If a bi-weekly payment was missed, work would stop immediately and resume only upon receipt of payment. I thought that protected me.
The first installment arrived. Roughly $18,000. I paid my subcontractors. I paid my core team. Work continued.
The second installment did not arrive.
I stopped work as agreed. The client champion reached out. Growing fast, new CFO settling in, moving in the right direction. He believed what he was telling me, or at least he seemed to. A few of my trusted associates were in the middle of critical path work. I did not want to pull them off the project if this was a two-week delay. I kept them working.
Two weeks later I received a different kind of call.
The company had filed for bankruptcy in Delaware. The one with 100 agents processing orders in real time, the one that had taken over a television studio, the one that was going to change mobile media, was done. It turned out that even the client champion had not been told the full picture.
I had collected roughly $120,000 on a $360,000 project that was about one-third complete. I had associates who had done the work in good faith. I made every one of them whole plus a little extra for the disruption. That was not negotiable.
Over the next six months the Delaware bankruptcy court worked through the case. Larger agencies with secured creditor positions were made whole. Some took possession of hard assets, including company vehicles. I watched that process from the unsecured creditor line.
Then came the ruling I had not anticipated.
The court determined that by modifying my payment terms mid-project, I had demonstrated knowledge of my client’s financial distress. The accommodation I had made to be helpful was treated as evidence that I knew they were struggling and had renegotiated terms to extract money before the collapse. They ordered me to return one-third of what I had already collected.
I had lost the $240,000 still owed for work not yet paid. I was now also returning $40,000 I had already earned, deposited, and used to pay my team. The total damage was roughly $280,000. For a small agency, that is not a bad quarter. That is an existential hit.
Here is what I know now that I did not know then.
Your payment terms are not just a collection mechanism. They are a legal record of what you understood about your client’s financial condition at the time you signed them. When those terms change, you have created a document that a bankruptcy court can read as evidence of what you knew and when you knew it.
A company with healthy cash flow does not ask its vendors to restructure installments. A company that cannot meet the payment schedule it agreed to is telling you something, even when the people inside it do not fully understand what they are telling you.
Do not change your payment terms mid-project. Not for cash flow. Not as a courtesy. Not because the client is a good partner and you trust them. If the situation has changed enough to require new terms, the situation has changed enough to require a new decision about whether to continue at all.
I also learned something about contracts. I had a master services agreement. A legal team dissected it and turned it into a document that argued against me. A small agency cannot afford that fight. I now use plain English agreements. A stated prescription. Deliverables. A timeline. A payment schedule. Clear enough that a bankruptcy judge can read it and understand exactly what both parties agreed to.
The terms I sign are the terms I keep.
If I had walked away from that project the moment the second installment did not arrive, I would have been out one missed payment. Instead I stayed, trusted, and kept working.
That $280,000 lesson has a one-sentence prescription.
Never change your terms.
Richard D. Stuart
The Weekly Prescription

